Controlled demolition of a redundant steel framed building on a live HWRC site in Staffordshire.
The demolition was carefully planned to commence mid-afternoon on a Friday and was completed in the early hours of Saturday morning when the site was closed for business.
Upon re-opening the site at 8.00am the building was completely demolished and all the debris was safely stored in skips in readiness for off – site disposal.
Pre-demolition works included :
• Structural surveys
• Service disconnections / isolations
• Establishment of a well defined exclusion zone
• Liaison with South Staffs Council
• Development of a Demolition Plan
The refurbishment works included :
• Concrete hardstandings
• Push wall panels
• Walkways and handrailings
• Drainage diversions
• Installation of soakaways
FCC Commented : “DXI did an exceptionally well planned job without a hitch and delivered on time to the highest quality, with a committed and dedicated team
CLIENT
FCC Environment Limited
REFERENCE CONTACT
Delvis Firth ; FCC Environment Ltd
CONTRACT VALUE
£136K
CONTRACT DETAILS
Controlled demolition of redundant steel framed and cladded building & associated refurbishment works within a “live” HWRC