The works comprised the installation of 12,500m2 of a Geosynthetic capping layer to an operation landfill site to allow the site to be progressively restored

The capping layers comprised 300mm regulating layer excavated from on-site stockpiles. This was overlain by a 1mm thick welded Linear Low Density Polyethylene (LLDPE) geomembrane liner, a Geosynthetic Drainage Layer (GDL) and 1m thickness of restoration soils.

Sampling and testing of the permanent works materials was a pre-requisite for regulatory sign off of the completed works.

Haul distances were on average greater than 700m and the project was completed on time despite having to commence the works in Q3 of 2015.

  • CLIENT

    FCC Environment Ltd

  • REFERENCE CONTACT

    Tim Darby, FCC Environment Ltd

  • CONTRACT VALUE

    £200K

  • CONTRACT DETAILS

    Installation of a Geosynthetic cap to a Landfill

  • SHARE

See how DXI can work for your project

Services

What Our Clients Say

Services
Contact

DXI Regeneration Limited

Head Office:
DXI Regeneration Ltd
Landgate Business Centre,
Wigan Road,
Ashton-in-Makerfield,
Wigan,
WN4 0BX

Tel: 01942 720325

North Wales Office:
DXI Regeneration Ltd
Trinity Square Business Centre,
3 Trinity Square,
Llandudno,
Conwy,
LL30 2PY

Website Terms & Conditions
Privacy Policy

© 2019 DXI Regeneration Limited.
Registered in England & Wales No 8718376.

Contact